We are continuing the work in your building. The third floor walkway repairs and stucco demolition in the vicinity is in progress. We are currently conducting the windows, sliding doors, and door pan removal and installation for specific units. This project will require interior access to your unit. Work also includes the stucco lath installation to begin re-applying stucco on the exterior of the building. These projects will entail noise from drilling into exterior walls, walkway demolition of the third floor, hammering on the stucco, power tools in the interior of certain units, and general construction related noise. There will also be dust, debris and modified access on the third floor area. We continue to apologize for the inconvenience. Please do not hesitate to reach out with any concerns you may have.

Sincerely,

The Management Team at Welch Road Apartments

 

Project: Structural Improvement & Moisture Proofing
Location: Building 1160
Project Status: In Progress
Location Start Date: March 7, 2022

 

Detailed Description Occurring Next Week:

Project Description Area/Units Impacts Noise Level Estimated Start Date* Estimated Completion Date*
Windows, sliding doors, door pan removal 633-634 Noise, dust, debris, interior access MEDIUM 04.05.2022 04.08.2022
Windows, sliding doors, door pan removal 625-626 Noise, dust, debris, interior access MEDIUM 03.30.2022 04.04.2022
Windows, sliding doors, door pan removal 623-624 Noise, dust, debris, interior access MEDIUM 04.07.2022 04.12.2022
Windows, sliding doors, door pan removal 612-615 Noise, dust, debris, interior access MEDIUM 04.01.2022 04.06.2022
Third floor walkway repairs Third Floor Noise, dust, debris, modified access HIGH 03.07.2022 TBD
Stucco Lath Installation Entire Building Noise, dust, debris, balcony access MEDIUM 04.04.2022 06.01.2022

*The dates on this schedule are estimated and may be subject to change which can be attributed to unforeseen delays in construction. We will notify you as soon as possible should this occur. If you have any questions please feel free to contact our leasing office at 650-497-0101 or email us at welchroadapartments@stanford.edu.