The HVAC installation work begins the final phase of construction in your building. For some of you, this work may include the initial unit interior inspection walks, while others may already be scheduled for demolition, installation, inspections, and interior repairs this upcoming week. The third floor walkways repair is in progress. The second floor walkways repair has begun this week. Work also includes the stucco lath installation to begin re-applying stucco on the exterior of the building. These projects will entail noise from hammering, power tools, and general construction related noise. There will also be dust, debris and modified access on the third floor area, second floor area, balconies, and the interior of your unit. We continue to apologize for the inconvenience. Please do not hesitate to reach out with any concerns you may have.
Sincerely,
The Management Team at Welch Road Apartments
Project: Structural Improvement & Moisture Proofing
Location: Building 1170
Project Status: In Progress
Location Start Date: January 17, 2022
Detailed Description Occurring Next Week:
Project Description | Area/Units | Impacts | Noise Level | Estimated Start Date* | Estimated Completion Date* |
HVAC Installation: Interior repair | 735-736 | Noise, dust, debris | MEDIUM | 03.14.2022 | 03.23.2022 |
HVAC Installation: Installation, inspection, interior repair | 733-734 | Noise, dust, debris | MEDIUM | 03.16.2022 | 03.25.2022 |
HVAC Installation: Interior walk, demolition, installation, inspection | 731-732 | Noise, dust, debris | MEDIUM | 03.21.2022 | 03.30.2022 |
HVAC Installation: Interior walk, demolition, installations | 725-726 | Noise, dust, debris | MEDIUM | 03.23.2022 | 04.01.2022 |
Third floor walkway repairs | Third Floor | Noise, dust, debris, modified access | MEDIUM | 01.18.2022 | TBD |
Second floor walkway repairs | Second Floor | Noise, dust, debris, modified access | MEDIUM | 03.21.2022 | 04.04.2022 |
Stucco lath installation | Entire Building | Noise, dust, debris, modified access | MEDIUM | 03.07.2022 | 04.04.2022 |
*The dates on this schedule are estimated and may be subject to change which can be attributed to unforeseen delays in construction. We will notify you as soon as possible should this occur. If you have any questions please feel free to contact our leasing office at 650-497-0101 or email us at welchroadapartments@stanford.edu.