Notice of Upcoming Metal and Decorative Railing Installation: Building 1160

Notice of Upcoming Metal and Decorative Railing Installation: Building 1160

NOTICE
Start Date
Thu Apr 28, 2222 - 12 AM

Dear Resident of Building 1160,

 

We hope this finds you well. We are writing to let you know that as part of the exterior repairs and reconstruction project our contractors will require access to your patio and balcony for the metal rail installation. To complete these repairs, we will need 3.5 hours per unit. We anticipate the construction timeline to occur over a three (3) week period, barring any changes or delays which may extend the forecasted schedule below.

Balcony/Patio Access Dates Morning Unit #
8:30 am - 12:00 pm
Afternoon Unit #
12:30 pm - 4:00 pm
May 16, 2022 636 635
May 17, 2022 634 633
May 18, 2022 632 631
May 19, 2022 626 625
May 20, 2022 624 623
May 23, 2022 622 621
May 24, 2022 616 615
May 25, 2022 614 613
May 26, 2022 612 611
May 27, 2022 to June 3, 2022 Courtyard / Common Areas

Please Note: This project will require contractors to access the patio or balcony attached to your unit. Access to your individual patio or balcony to perform the work will take approximately 3.5 hours for each unit. There will be no railing installation work on May 30, 2022 in observance of Memorial Day.

Additional Guidelines are provided to you as reference prior to start of work and during the reconstruction phase of the project:

  1. Clear Work Areas: Please clear any personal belongings, door mats, plants, etc at least 4 feet from the work area.
  2. Keep Windows and Doors Closed: Please keep all windows, doors, and associated window coverings near work areas closed during construction.
  3. Work Hours: The Contractor's working schedule is from 8:00 am to 4:30 pm Mondays through Fridays (excluding major Holidays). Please refrain from the work areas during this time. There will be days that the contractor may not be working on-site to allow applied building products sufficient curing/drying time.
  4. Noise: There will be sporadic, elevated noise from the construction work.
  5. Dust: There may be minor dust resulting from construction work.
  6. Contractor Identification: All Contractor field employees will be identified with company safety vests or attire.
    • Please do not approach the workers under any circumstances unless it is an emergency. If you have to pass the work area for any reason, please maintain the regulated six (6) feet distance.
    • All contractors will be wearing face masks for protection and safety.
    • All contractors will be undergoing daily temperature checks prior to start of work.
    • Any contractor who shows symptoms of being sick will not be allowed onsite.
  7. Pets: Please keep all pets, animals, and children safely secured indoors away from the work area.
  8. Notice and Schedule Changes: This Notice will serve as Notice to Resident. This schedule may be subject to changes, delays, work modifications and operational adjustments due to implementation of safety protocols (including social distancing, sanitation, and other procedures due to Coronavirus/COVID-19), weather, additional damages uncovered, any delays related to mock-ups, additional inspections and testing, value engineering or repair processes, other unforeseen conditions and/or any other issues outside of the construction team's control.
  9. Stay Alert: Please be careful and stay aware of your surroundings when you enter and exit. Access may be rerouted during this period. Please follow the signs accordingly.

We apologize for the inconvenience and thank you for your attention and for your cooperation. For questions, please contact us at (650) 497-0101, or send us an email at welchroadapartments@stanford.edu

 