We are starting the reconstruction work of the exterior of the building. Scaffolding will be set up as well as temporary protection to ensure residents' safety. Stucco demolition will begin next week to remove the stucco around the windows on the exterior of the building. Work also includes repairing the third floor walkways. These projects will entail noise from drilling into exterior walls, walkway demolition of the third floor, hammering on the exterior stucco around your windows, and general construction related noise. There will also be dust, debris, and modified access on the third floor area. Stucco demolition will not require access to your sliding glass doors or balconies this week. We continue to apologize for the inconvenience. Please do not hesitate to reach out with any concerns you may have.

Sincerely,

The Management Team at Welch Road Apartments

 

Project: Structural Improvement & Moisture Proofing
Location: Building 1150
Project Status: In Progress
Location Start Date: June 13, 2022

 

Detailed Description Occurring Next Week:

Project Description Area/Units Impacts Noise Level Estimated Start Date* Estimated Completion Date*
Temporary protection and scaffolding set up Entire Building Noise, dust, debris HIGH 06.13.2022 06.23.2022
Stucco demolition Entire Building Noise, dust, debris, modified access HIGH 06.13.2022 06.21.2022
Third floor walkway repairs Third Floor Noise, dust, debris, modified access HIGH 06.22.2022 07.06.2022

*The dates on this schedule are estimated and may be subject to change which can be attributed to unforeseen delays in construction. We will notify you as soon as possible should this occur. If you have any questions please feel free to contact our leasing office at 650-497-0101 or email us at welchroadapartments@stanford.edu.