Project Status Update: Building 1160
Dear Residents,
We are starting the reconstruction work of the exterior of the building. Scaffolding will be set up as well as temporary protection to ensure residents' safety. Work also includes repairing the third floor walkways. These projects will entail noise from drilling into exterior walls, walkway demolition of the third floor, sawing, and general construction related noise. There will also be dust, debris and modified access on the third floor area. We continue to apologize for the inconvenience. Please do not hesitate to reach out with any concerns you may have.
Sincerely,
The Management Team at Welch Road Apartments
Project: Structural Improvement & Moisture Proofing
Location: Building 1160
Project Status: To Begin
Location Start Date: March 7, 2022
Detailed Description Occurring Next Week:
Project Description | Area/Units | Impacts | Noise Level | Estimated Start Date* | Estimated Completion Date* |
Temporary protection and scaffolding set up | Entire Building | Noise, dust, debris | HIGH | 03.07.2022 | 04.01.2022 |
Third floor walkway repairs | Third Floor | Noise, dust, debris, modified access | HIGH | 03.07.2022 | TBD |
*The dates on this schedule are estimated and may be subject to change which can be attributed to unforeseen delays in construction. We will notify you as soon as possible should this occur. If you have any questions please feel free to contact our leasing office at 650-497-0101 or email us at welchroadapartments@stanford.edu.