Project Status Update: Building 1170
Dear Residents,
We are continuing the work in your building, which includes updating your windows, sliding doors, and removing door pans. Work also includes the removal of the cement plastic around the windows, and repairing the third floor walkways. These projects will entail noise, dust, debris and modified access on the third floor area. We continue to apologize for the inconvenience.
Sincerely,
The Management Team at Welch Road Apartments
Project: Structural Improvement & Moisture Proofing
Location: Building 1170
Project Status: In Progress
Location Start Date: January 17, 2022
Detailed Description Occurring Next Week:
Project Description | Area/Units | Impacts | Estimated Start Date* | Estimated Completion Date* |
Windows, sliding doors, door pan removal | 715-716 | Noise, dust, debris | 02.14.2022 | 02.17.2022 |
Windows, sliding doors, door pan removal | 725-726 | Noise, dust, debris | 02.10.2022 | 02.15.2022 |
Windows, sliding doors, door pan removal | 733-734 | Noise, dust, debris | 02.17.2022 | 02.24.2022 |
Removal of cement plastic around windows | Entire Building | Noise, dust, debris | 01.31.2022 | 02.18.2022 |
Third floor walkway repairs | Third Floor | Noise, dust, debris, modified access | 01.18.2022 | TBD |
*The dates on this schedule are estimated and may be subject to change which can be attributed to unforeseen delays in construction. We will notify you as soon as possible should this occur. If you have any questions please feel free to contact our leasing office at 650-497-0101 or email us at welchroadapartments@stanford.edu.